Gf3xx-series have a lead time of approximately 15 working days. (adding additional lenses to this camera range will extend the lead time by another 5 days due to calibration schedules)
G300a (60Hz) have a lead time of approximately 15 working days. (adding additional lenses to this camera range will extend the lead time by another 5 days due to calibration schedules)
The following items are on demand, please contact ordersupport@flir.com for lead times:
GF343
GF346
GF304
GF620-Series have a lead time of approximately 10 working days.
This can only be met if the following requirements are met:
- You have submitted a completed FLIRtis document with detailed information of the end-user and the end-use - Non-EU/Non-US orders only
- (if your payment term is CIA) the build time will kick off as soon as your payment has been received